Sonotube Remaining Fill Calculator

See how much is left after part of the pour.

Fill & Elevation

See how much is left after part of the pour.

⚙️Calculation Parameters

inches
inches
%
Bag Yield Standard:ASTM C387 (0.60 ft³/80lb)

📊Calculated Output

Cubic Yards (yd³)
0.36
Ready-mix truck volume
Cubic Feet (ft³)
9.60
Total wet concrete volume
80 lb Premix Bags
16
@ 0.60 cu.ft per bag
60 lb Premix Bags
22
@ 0.45 cu.ft per bag
Metric Volume:0.272 m³ (272 L)
Estimated Concrete Weight:~1,392 lbs (631 kg)
Mixing Water Required:~12.0 gal (~45 L)
Per Tube Volume:2.18 ft³ (0.081 yd³)

How Sonotube Remaining Fill Calculator Works?

To find the remaining fill, the Sonotube Remaining Fill Calculator subtracts the concrete already placed from the total the tubes need. The process takes 4 steps.

  1. Enter the project volume

    Type the tube size and count, or the planned total in cubic feet (ft³) or cubic yards (yd³).

  2. Enter what is placed

    Type the volume poured so far, or the number of bags mixed and placed.

  3. Subtract

    The calculator removes the placed volume from the planned volume.

  4. Read the shortfall

    The tool shows the remaining ft³, yd³ and bags, rounded up to whole bags.

Sonotube Remaining Fill Calculator Formula

The Sonotube Remaining Fill Calculator subtracts placed volume from required volume.

Remaining volume

V_rem = V_total − V_placed

Both in ft³ or both in yd³.

Placed from bags

V_placed = bags placed × yield

80 lb = 0.60 ft³ per bag.

Bags left

Bags = ⌈V_rem ÷ yield⌉

Round up to a whole bag.

Worked example: 8 tubes at 12 in × 48 in, 30 bags of 80 lb placed

  1. V_total = 8 × 3.142 = 25.13 ft³
  2. V_placed = 30 × 0.60 = 18.00 ft³
  3. V_rem = 7.13 ft³, so mix 12 more bags of 80 lb concrete

Sonotube Remaining Fill Calculator Conversion Table

The remaining fill conversion table tracks a job of 8 tubes at 12 in × 48 in (25.13 ft³, 0.93 yd³) as 80 lb bags go in.

Remaining fill after bags placed
Bags placedPlaced ft³Remaining ft³Remaining yd³Bags still needed
0 bags0.0025.130.93142
10 bags6.0019.130.70932
20 bags12.0013.130.48622
30 bags18.007.130.26412
40 bags24.001.130.0422
50 bags30.000.000.0000

Values use net volume with no waste. Add 1 or 2 bags, if holes run wider than the tubes.

What is Sonotube Remaining Fill Calculator?

A Sonotube Remaining Fill Calculator is a mid-pour tool that tells you how much concrete is still needed to finish filling your tubes.

Pours stop for many reasons: a mixer breaks, the day ends, or the bag pile runs out. The calculator answers the next question on the spot. A crew that planned 8 piers and placed 30 bags of 80 lb mix still needs 12 bags.

The tool accepts placed volume as bags, as cubic feet or as a list of completed tubes.

What are the uses of Sonotube Remaining Fill Calculator?

There are 4 main uses of the Sonotube Remaining Fill Calculator.

  • Second store run

    DIY builders buy exactly the bags still needed.

  • Next-day pours

    Crews plan day 2 of a pour split over 2 days.

  • Truck top-off orders

    Contractors call a final small load from the plant.

  • Crew handoffs

    Supervisors pass a clear remaining quantity to the next shift.